Booysendal

Reserves and resources

Booysendal UG2 mine reserve estimate asáatá30áJuneá2011
    3PGE+Au
Orebody Category Mt g/t Moz
Merensky reef Proven
  Probable
  Total
UG2 reef Proven 30.64 3.08 3.03
  Probable
  Total 30.64 3.08 3.03
Combined reefs Proven 30.64 3.08 3.03
  Probable
  Total 30.64 3.08 3.03
Booysendal UG2 mine resource estimate asáatá30áJuneá2011
    3PGE+Au
Orebody Category Mt g/t Moz
Merensky reef Measured
  Indicated
  Inferred
  Total
UG2 reef Measured 43.64 4.16 5.84
  Indicated
  Inferred
  Total 43.64 4.16 5.84
Combined reefs Measured 43.64 4.16 5.84
  Indicated
  Inferred
  Total 43.64 4.16 5.84
Booysendal north resource estimate asáatá30áJuneá2011
    3PGE+Au
Orebody Category Mt g/t Moz
Merensky reef Measured 33.30 5.37 5.75
  Indicated 46.34 5.43 8.08
  Inferred 85.26 5.25 14.39
  Total 164.90 5.32 28.22
UG2 reef Measured 51.73 3.88 6.45
  Indicated 46.23 4.66 6.92
  Inferred 230.81 3.34 24.82
  Total 328.77 3.61 38.19
Combined reefs Measured 85.03 4.46 12.20
  Indicated 92.57 5.04 15.00
  Inferred 316.07 3.86 39.21
  Total 493.67 4.18 66.41
Booysendal south resource estimate asáatá30áJuneá2011
    3PGE+Au
Orebody Category Mt g/t Moz
Merensky reef Measured 3.80 2.46 0.30
  Indicated 15.97 3.15 1.62
  Inferred 70.80 3.69 8.40
  Total 90.57 3.54 10.32
UG2 reef Measured 14.60 3.41 1.60
  Indicated 52.90 3.43 5.84
  Inferred 140.60 2.94 13.30
  Total 208.10 3.10 20.74
Combined reefs Measured 18.40 3.21 1.90
  Indicated 68.87 3.37 7.46
  Inferred 211.40 3.19 21.70
  Total 298.67 3.23 31.06
Booysendal prill splits
  % metal content
Prill splitsPtPdRhAuCu%Ni%
UG258.132.08.91.00.0090.075
Merensky58.531.52.47.60.1250.272
Combined58.331.86.53.40.0520.149

UG2 resource classes

UG2 resource classes
 

Merensky resource classes

Merensky resource classes
 

Mineral resource and reserve statement

Booysendal location within the Bushveld Complex

Booysendal property

Map of the Booysendal property