Printer friendly Printer icon

Company publications

Northam concludes Booysendal feasibility study

8 October 2009

095/09/mb

Key features

Northam Platinum Limited is pleased to report that the Booysendal feasibility study report is complete and is in the process of being compiled, while a review of the design and layout is under way. Final board approval for the project is expected early in calendar year 2010.

Northam's acquisition of the Booysendal project became effective in August 2008, with work on the feasibility study having begun in June 2008. Booysendal is located on the eastern limb of the Bushveld Complex, near the town of Lydenburg.

Commenting on the results of the study, Northam CEO Glyn Lewis said today, "The feasibility study has confirmed our approach to the project. Booysendal is living up to our expectations and is likely to be a significant, long-life producer, and one of the new-generation PGM mining projects of the future.

"The mining plan confirms that a modular approach, initially focussing on the UG2 reef, should be implemented. The plan is to mine at a rate of 150 000 tonnes per month and upgrade this production through a Dense Media Separation ("DMS") plant to produce a concentrator feed of 120 000 tonnes per month. The second module will have a similar production profile when it is brought into operation, resulting in a total concentrator fed of 240 000 tonnes milled per month. For module 1, at full capacity, in mid 2009 money terms, the average operating cost is expected to be R410 per tonne mined.

"These operating parameters are expected to give rise to sales of some 130 000 ounces (3PGM+Au - platinum palladium, rhodium, gold) per annum on completion of module 1, rising by a further 115 000 ounces (3PGM+Au) per annum, to a total of 245 000 ounces (3PGM+Au) for both modules.

"The capital cost for module 1 is expected to be R3.0 billion (in 2009 terms) over a five-year period with similar capital expenditure anticipated for module 2. Our intention remains to fund the project through a combination of a rights issue, internal retentions and medium-term bank debt."

Northam will begin the construction of an access road and water pipeline and start the boxcut for the module 1 on-reef decline in the first half of 2010. First concentrate from module 1 is anticipated in 2013, reaching full production in 2015. Module 1's life-of-mine is expected to exceed 20 years, during which period further production expansions would be developed.

The national power utility, Eskom, has undertaken a feasibility study for an 80MVa substation to be situated on the Booysendal property. Eskom is currently also in the process of conducting the Environmental Impact Assessment (EIA) study for the transmission lines from the nearby Steenberg sub-station. The application for the first 20MVa has been submitted and a budget quote is awaited. Our critical path analysis has identified the supply of electricity as a key factor.

The conversion of Booysendal's old order mining right to a new order mining right over nine of the 11 farms was executed on 10 September 2009. The application for new order mining rights on the remaining two farms and the transfer of the Der Brochen extension is in progress.

The scale of Booysendal, together with the accessibility of the reef horizon from surface, provides the project with significant inherent flexibility and growth potential. Further expansions of the mine (such as increasing the UG2 mining rate, or exploitation of the Merensky reef) will be the subject of a further feasibility study.

Further updates will be provided to the market in due course.

Key features: Booysendal feasibility study

Key features of the Booysendal project arising from the feasibility study are:

Modular approach

Access to the reef

Throughput

Anticipated costs

Environmental permitting

Timing and production build-up

Estimated Production Ramp up
 
Estimated PGE Production Build up

Capital costs

 
Estimated Capital Expenditure

Smelting

Power supply

 

About Northam and Booysendal

Northam Platinum Limited (Northam) is the only fully independent, black-owned and controlled integrated PGM producer listed on the JSE Limited (JSE). The company wholly owns and operates the cash-generative Zondereinde platinum mine and metallurgical complex on the upper end of the western limb of the South African Bushveld Complex near the town of Thabazimbi.

Northam is planning to develop its wholly-owned 103 million ounce (3PGM+Au) Booysendal project, which is located near Lydenburg on the eastern limb of the Bushveld Complex. In addition, the company holds a 7.5% interest in the Pandora joint venture, a PGM mining operation on the western limb of the Bushveld Complex, near Brits, in partnership with Anglo Platinum, the Bapo Ba Mogale community and Lonmin.

The company has a combined resource base of 130 million ounces (3PGE+Au) (including 8.1 million ounces (3PGE+Au) in mineral reserve at Northam's Zondereinde mine). The progressive development of Booysendal will add some 245 000 ounces (3PGM+Au) to the company's existing annual output of some 300 000 ounces (3PGM+Au) with more than 50 years life-of-mine. As an independent, fully integrated PGM producer, Northam has full control over the entire PGM beneficiation stream of its metals from mine to market.

Distributed by:

Russell & Associates, Johannesburg
Tel: +27 (0)11 880 3924
Fax: +27 (0)11 880 3788

Northam will be hosting a presentation of the feasibility study results. Details as follows:

^Back to top

® 2008 Northam Platinum Limited